Archive for the ‘Progress Report’ Category
Site impressions
September 3rd, 2010 by Tim Delhey Eian- Southeast elevation
- Front entry canopy roof and accent wall
- Rain gardens and south facade
Facade revealed
August 28th, 2010 by Tim Delhey Eian
This weekend marks a milestone in the build of the Passive House in the Woods. For the first time, the EIFS facade is revealed after months of “the cooler” (white EPS), and a short stint of lots of scaffolding.
First Finishes
August 13th, 2010 by Tim Delhey EianThis week we’ve gotten the first glimpse of the exterior finish. The color changes a bit with the exposure to sunlight, and the finish in the photo is not fully cured, yet. Nonetheless, the color is spot on and works perfectly with the setting as intended. This is an exciting step, as most of the team have gotten very used to the white of the EPS insulation over the last few months. As mentioned earlier, a lot is happening at the house. The next 2-3 weeks are going to present the biggest changes in terms of finishes the house has seen so far.
Progress Report
August 1st, 2010 by Tim Delhey EianThe final weeks of construction lie ahead of the team. The mechanical rough in work is essentially complete and finishes are now being installed.
On the inside, casein (milk) paint adorns the ceilings, while earthen plaster from American Clay is going on interior walls. Harvested oak from the site has been milled and finished by Wood from the Hood and will find its way back into the house as interior window sills, trim, and stair treads and risers. Cabinets from Partners for Design—manufactured by Crystal Cabinets—are under construction in their woodshops. The interiors were designed in partnership with InUnison Design, who are bringing a wealth of experience and style to this project. We are very excited to see one space after the next receive its final finishes, and the concept of “warm modern” come to life.
On the outside, the exterior insulation and finish system is being installed, exterior shades are being mounted, and some of the site has been graded. Laurie McRostie is working with Gary to finalize the landscape plan and the exterior steel structure is being prefabricated. The exterior work will eventually change the white styrofoam look that we have gotten so familiar with over the past six months, and give the Passive House in the Woods its final face.
The team is shooting for substantial completion at the end of the month. August will be an exciting month at the Passive House in the Woods. We plan to open the home up to the public again in September and October. Stay tuned for announcements.
Progress Report
June 15th, 2010 by Tim Delhey EianThe rough-in stage is now nearly complete. Sheet rock is going up all throughout—actual rooms are starting to emerge from the rough look that has become so familiar in recent weeks. With most mechanical systems completed or well under way, the end is now more in sight than ever. The last shop drawings are going through the review process now, allowing for construction of cabinets and exterior structures. The next few weeks are going to reveal the interior design package that Christine Frisk and Erin Heikkinen of InUnison Design have been working on, as well as the lighting scheme that Carol Chaffe of Chaffee Associates designed.
First Blower Door Test successfully completed
June 6th, 2010 by Tim Delhey EianWith the help of Gary Nelson of the Energy Conservatory in Minneapolis, we were able to conduct a first series of blower door tests. We pressurized and depressurized the building, and used a smoke generator to identify leaks. This was an amazing process and helped us gain a great deal of understanding for the little details that make a building air-tight. In the end, the building delivered an average of 0.36 ACH50. We are excited to have surpassed the Passive House requirement of 0.6 ACH50 during this preliminary test.
Mechanical Systems
May 28th, 2010 by Tim Delhey EianThe building is currently in the “rough-in” stage, which means that electrical, plumbing, and mechanical systems are being installed.
Electrical
Both line and low voltage wiring are installed by EHS. They take great care in a clean installation that is easy to understand. Low voltage and line voltage lines are run in separate bundles in an effort to keep signals within undisturbed.
The electrical system in a Passive House is similar to ordinary electric systems with the exception that any protrusion through exterior walls or the roof are being sealed for air-tightness and uninterrupted insulation.
Gary chose to have a lighting control system by Lutron installed. This is not required by the Passive House standard but can help reduce lighting-related energy loads.
Plumbing
The plumbing system is very simple. The design of the home puts most of it in one single wall that extends vertically from the basement to the second floor throughout the home. This means short waste and supply pipe runs, and an economical installation. The supply lines are copper, and continuously insulated for efficiency. The waste lines are PVC, and mostly insulated. Warm waste water is used to pre-warm the well-water that is being pumped into the hot water tank, upping the efficiency of the hot water system. Additionally, hot water is being pre-heated by a solar thermal collector on the roof. Last but not least, an electric on-demand water heater can boost the water temperature if the combination of waste-water heat recovery and solar thermal pre-heating do not make it hot enough. 85% of the hot water needs will not require the on-demand unit.
The plumbing system in a Passive House is similar to ordinary plumbing systems with the exception that pipe runs are continuously insulated, and that air-admittance valves are being used instead of vent stacks.
Ventilation
The ventilation system is at the heart of each Passive House. This building will utilize a Passive House certified Lüfta heat recovery ventilator from Germany, supplied by Peak Building Products. It will be combined with a 600 foot PEX earth loop provided by Rehau—buried below frost on the property. This system will pre-warm, or pre-cool and dehumidify the incoming ventilation air and boost the system’s efficiency to well above 90%. The Luefta machine will supply the entire home with outside air year-round, and exhaust air from the bathrooms and kitchen. The ductwork comes from Inno-Products and is comprised of a home-run layout with 3″ diameter plastic flex-ducts. The systems throughput is being adjusted by sensors that measure both CO2 and humidity levels in the air. This setup means that the homeowner does not have to adjust ventilation rates, and that the system will ramp down when it’s not needed to conserve energy.
Backup Heating

Nuheat standard mats
Nuheat is supplying electric in-floor heating mats on room temperature thermostats. There are 7 zones throughout the home that can be individually adjusted. The entire system is sized to supply a peak heat load of 10 kBtu—about 3,000 Watts, or the equivalent of running 2 hair dryers at the same time. This represents a 90% reduction in heating system over most conventional construction today.
The heating system in a Passive House is very different from ordinary heating systems. It is merely a backup for long stretches of extremely cold and cloudy days in the winter and does not compare to conventional systems in terms of its capacity.
Renewable Systems
Energy Concepts helped with the design of the renewable energy systems. There are three systems that will go into the building: A solar photovoltaic tracker, a photovoltaic panel array, and a solar thermal domestic hot water system. The photovoltaic systems are scheduled to produce about 6,750 kWh of electricity annually, while the solar thermal panel has the capability to pre warm enough domestic hot water to provide 85% of the annual demand. The remaining portion of heat needed will be supplied with the help of a Stiebel-Eltron booster heater.
Ductwork 2.0
May 21st, 2010 by Tim Delhey EianThis picture shows the ventilation ductwork inside the Passive House in the Woods. Supplied by Peak Building Products, this German-sourced product makes individual connections from the ventilation machine to each location, without sheet metal, mastic, duct tape, and leaks.
Optiwin Windows arrive from Germany
May 21st, 2010 by Tim Delhey EianToday, the Optiwin windows from Germany that Peak Building Products supplied arrived at the site.
Mini Series Part 3: Assembly Design
May 12th, 2010 by Tim Delhey EianAs Passive House designers, we are concerned with air-tightness and insulation value, as well as indoor environmental quality, hygrothermal performance, embodied energy, and green interior design. We selected construction methods and materials that combine highest performance with durability, robustness, and reasonable environmental impact. We preferred local product where suitable, and specialized product as needed to meet performance and aesthetic goals–always with a focus on the client’s vision, sustainable design, and the greater good.
Passive House performance is in the details. We meticulously defined air-barrier, vapor barrier, and insulation thickness at any junction, and made sure that they are continuous throughout.
Careful assembly design and detailing plays a huge roll in high-performance buildings. This is our specialty and we bring years of experience to this process. During the construction process, we assist the general contractor with site observations to help see details all the way through production. After all, it is on the job site where the performance is built.
Tomorrow: Powered by Electricity?










































































